Until sericulture facilities of the world maximum scale "NSP Yamaga factory" will be done

Construction scenery of NSP Yamaga factory

April 1, 2016 Completion of dismantling and leveling of former Kosaka elementary school

July 27, 2016 A groundbreaking ceremony before construction started

August 30, 2016 Foundation work

September 7, 2016 Constant foundation construction

September 15, 2016 Every day the foundation of the factory is built at the scene

September 20, 2016 Concrete placement for the area of the factory is completed. Still the foundation consolidation goes on

September 30, 2016 The framework of the foundation is stretched all over. Construction will go on rainy days as well

October 6, 2016 Concrete is laid on the assembled framework to strengthen the foundation

October 14, 2016 Foundation is nearly complete. Wait for buildup

October 18, 2016 Construction of the skeleton of the factory which began at last. From here, at one stroke, the world's largest sericulture factory reveals its appearance

October 19, 2016 A site where various heavy machinery are introduced. The scenery changes with every moment

October 24, 2016 The season is from summer to autumn. As the seasons, the scenery changes. Towards the future

October 26, 2016 Each time a pillar is added, its size will become concrete shape

October 31, 2016 The skeleton approaches completion. To overwhelming size, excitement can not be stopped

November 3, 2016 The skeleton is completed. New scenery will be created clear sky in Yamaga

November 18, 2016 A scaffold for exterior construction is assembled so as to be wrapped in a cocoon

November 21, 2016 Scaffold covered with scaffold. Exterior work progresses in a net like a cocoon

November 25, 2016 Like a heartbeat, construction continues

December 24, 2016 You can not know the inside of the cocoon from the outside. Among them, factories are being formed by many people's hands

December 28, 2016 Towards the creation of new silk, we will continue to make factories today

January 6, 2017 It's to larva from a cocoon. As if emerging, the net covering the factory will be removed

January 9, 2017 A factory is beginning to see the whole picture gradually. Even until it completely shows up

January 9, 2017 The NSP Yamaga factory is showing its appearance. The exterior is almost completed

April 28, 2017 Finally completed, NSP Yamaga factory. The new silk sericulture plan starts from here

April 28, 2017 Silk material is used everywhere in the interior. Next, The cocoon I produced at a NSP Yamaga factory is coloring various living